ACTUALITE Aéronautique

Vous souhaitez réagir à ce message ? Créez un compte en quelques clics ou connectez-vous pour continuer.
ACTUALITE Aéronautique

ACTUALITE Aéronautique : Suivi et commentaire de l\'actualité aéronautique

-10%
Le deal à ne pas rater :
-30€ sur la nouvelle Tablette tactile Lenovo Tab Plus – 11.5” ...
269.99 € 299.99 €
Voir le deal

    Nouvel aéroport de Berlin

    Poncho (Admin)
    Poncho (Admin)
    Whisky Charlie


    Nouvel aéroport de Berlin Empty Nouvel aéroport de Berlin

    Message par Poncho (Admin) Jeu 10 Mai 2012 - 10:00

    Bonjour à tous

    Le nouvel aeroport de berlin qui va réutiliser une partie des infrastructure de Schoenefeld

    http://en.wikipedia.org/wiki/Berlin_Brandenburg_Airport

    Ne sera pas prête dans le délai prévu

    http://www.aviationweek.com/Article.aspx?id=/article-xml/avd_05_09_2012_pNaN-01-455916.xml


    The delayed opening of Berlin’s new international airport could cause chaos for Luft—hansa and Air Berlin, both of which are trying to minimize the potentially dramatic consequences of the deferred launch of operations.

    Berlin’s airport operator, Berliner Flughaefen, today announced it will be impossible to keep the projected June 3 opening date, with CEO Rainer Schwarz attributing the delay to the terminal’s fire protection system.

    That system has failed recent tests, and further testing is needed to ensure everything works properly, Schwarz said.

    Schwarz did not specify how extensive the delay will be, although Berlin Mayor Klaus Wowereit said later he hoped the airport could be opened in late August. Some industry sources are more skeptical.

    Airlines doubt that fire protection is the only issue affecting the current schedule. “We have had to realize over the past few days and weeks and after several tests that there is a need to act on several fronts,” says Lufthansa. And while the airline is not officially specifying the issues, company sources indicate that there is a general uneasiness concerning the state of check-in facilities at the airport.

    Schwarz stressed he is ready to stay in his position “in this difficult time.” However, Matthias Platzeck, the prime minister of the state of Brandenburg, noted that the delay was “more than a bad surprise” and that he was “very angry.” He said he expects a detailed plan by management by next Monday that specifies a recovery plan and new opening date.

    Brandenburg is the airport’s largest shareholder along with the city of Berlin.

    Berlin Brandenburg International (BBI) is intended to replace Berlin’s two existing airports Tegel and Schoenefeld. Tegel, the city’s main airport, is operating at capacity.

    BBI originally was scheduled to open in November 2011, but terminal modifications caused a delay of six months.
    This latest delay is a huge blow for both Lufthansa and Air Berlin. Lufthansa has planned to increase capacity 40% from Berlin, opening 50 more destinations, and was scheduled to base six more Airbus A320s in the country’s capital and introduce a low-fare scheme to stimulate demand. Air Berlin is currently building up a six-wave hub system and introducing long-haul services.

    Now the question is whether those plans have to be pushed back many months. But both carriers cannot simply cancel the additional flights; they have already sold tens of thousands of tickets and now are no longer sure whether they will be able to fly the planned schedules.

    Lufthansa says it plans to stick to its schedule and is securing additional slots at Tegel. However, even if it manages to get more slots on the already busy runways, it will be a huge challenge to process the additional passengers through Tegel’s crowded terminal.

    Moving part of Lufthansa’s or another operator’s flights to Schoenefeld is an alternative, although that would incur huge costs that would likely have to be covered by the airport company.

    Air Berlin says it is “very disappointed,” with CEO Hartmut Mehdorn noting that “this will cause huge logistics challenges and significant additional costs that we cannot yet calculate.”

    donc après un premier retard de 6 mois un second d'une saison semble se profiler

    Raison officielle : pb avec le système anti incendie ...
    D'autres raison semble s'ajouter

    A noter que la même excuse a été avancée pou la réouverture de la gare saint lazare en france (nouvelle galerie commerciale) il y a peut être eu du changement réglementaire dans l'air qui met le bouzin

    A suivre en tout cas, Lufthansa et Airberlin en position pas très agréagble


    _________________
    @avia.poncho
    Poncho (Admin)
    Poncho (Admin)
    Whisky Charlie


    Nouvel aéroport de Berlin Empty Re: Nouvel aéroport de Berlin

    Message par Poncho (Admin) Lun 7 Jan 2013 - 13:03

    Bon ben du retard en plus
    http://uk.reuters.com/article/2013/01/07/uk-germany-airport-idUKLNE90600S20130107

    Rien avant 2014 c'est au stade des rumeurs ... donc +2 ans dans la vue.



    (Reuters) - The
    opening of Berlin's new airport will be delayed again to at least 2014,
    more than two years later than originally planned after a series of
    embarrassing setbacks to what was meant to be a flagship project, a
    source familiar with the plans said.

    Nearly a quarter of a century
    after the Berlin Wall came down and 14 years after the government moved
    back to Berlin as the unified capital, Germany is still struggling to open an international airport to replace two from its Cold War past.
    The
    opening of the Berlin-Brandenburg Airport had been re-scheduled to
    October 2013, after already being postponed several times already over
    the past year due to problems, for example, with its fire safety
    systems.


    _________________
    @avia.poncho
    Poncho (Admin)
    Poncho (Admin)
    Whisky Charlie


    Nouvel aéroport de Berlin Empty Re: Nouvel aéroport de Berlin

    Message par Poncho (Admin) Mar 9 Avr 2013 - 14:20

    Tout va bien à Berlin
    Le trafic augmente Nouvel aéroport de Berlin 662529

    Mais le nouvel aéroport reste fermé

    http://www.usatoday.com/story/todayinthesky/2013/04/08/berlin-airport-fiasco-an-embarrassment-for-germans/2062533/



    German media have tracked down a list of tens of thousands of
    technical problems. Among them: Officials can't even figure out how to
    turn the lights off. Thousands of light bulbs illuminate the gigantic
    main terminal and unused parking lots around the clock, a massive energy
    and cost drain that appears to be the result of a computer system
    that's so sophisticated it's almost impossible to operate.
    Every
    day, an empty commuter train rolls to the unfinished airport over an
    eight-kilometer-long (five-mile) stretch to keep the newly-laid tracks
    from getting rusty, another example of gross inefficiency. Meanwhile,
    hundreds of freshly planted trees had to be chopped down because a
    company delivered the wrong type of linden trees; several escalators
    need to be rebuilt because they were too short; and dozen of tiles were
    already broken before a single airport passenger ever stepped on them.
    The
    airport itself points to problems with the fire safety system as the
    immediate cause of the delays: The fire safety system incorporates some
    75,000 sprinklers, but computer programming glitches mean it's not clear
    whether all of these sprinklers would spray enough water during a fire.
    And the system's underground vent system, designed to suck away smoke,
    isn't working. Here, again, technology's getting in the way: It's so
    advanced that technicians can't figure out what's wrong with it.
    Critics
    say that the difficulties with handling today's complex technology have
    been compounded by hasty, negligent work due to the intense time
    pressures.
    Underlying these problems appears to be a culture of political dishonesty.
    "Many
    politicians want prestigious large-scale projects to be inseparably
    connected with their names," said Sebastian Panknin, a financial expert
    with the Taxpayer's Association Germany. "To get these expensive
    projects started, they artificially calculate down the real costs to get
    permission from parliament or other committees in charge."
    In
    addition to that, politicians at the city, state and federal levels then
    often come with extra demands once construction is underway, which
    leads to expensive modifications. In the case of the Berlin airport,
    said Pankin, there were about 300 ad hoc change requests by politicians
    which created an explosion of costs and several delays - among them a
    last-minute wish to expand the terminal to include a shopping mall.
    "The
    airport is a classic example of the incompetence of our politicians,"
    said Sven Fandrich, a 28-year-old Berliner who works for an insurance
    company. "We've seen this happen with many big infrastructure projects
    in Germany. Nobody feels responsible. The politicians are more concerned
    about winning the next elections than devoting their service to the
    people."
    Hamburg's concert hall was to have opened by 2010.
    Instead it's nowhere near complete and costs have more than doubled to
    575 million euros. It's now due to open in 2016.
    Construction on
    Cologne's North-South subway line began in 2004. After cost overruns and
    a collapse that killed two people in 2009, officials say the entire
    line may not be open until 2019. Costs have soared from 780 million to
    1.08 billion euros.
    In Leipzig, the city tunnel for commuter
    trains was expected to open in 2009. Construction is still not finished,
    and costs have jumped from 572 million to 960 million euros.
    Of all the bungled projects, the Berlin airport is the biggest embarrassment.
    The
    initial plan foresaw building a stately airport that would be financed
    by private investors and replace the city's two Cold War airports -
    Tegel in former West Berlin and Schoenefeld in what was the communist
    east.
    After a series of disputes with private investors, the city,
    state and federal governments eventually took over the airport project.
    In 2006, costs were estimated at 2 billion euros, but after four
    delays, the figure spiked to 4.4 billion euros.
    Companies like Air
    Berlin, Germany's second biggest carrier, have been severely affected
    by the delays and are suing for lost revenues. Small businesses like
    coffee shops, restaurants, retail stores or bus operators - who had
    already hired staff and invested in new stores at the airport - are
    facing bankruptcy.
    Twitter users asked the mayor to "please open
    this gate," playing off President Ronald Reagan's famous 1987 appeal to
    Moscow to "tear down" the Berlin Wall.
    And by the time the airport finally opens, it may face a new headache.
    Some
    aviation experts are warning that by its inauguration date, the airport
    will already be too small to handle the rising number of passengers.
    The nearly 3.9 million square foot (360,000 square meter) airport
    complex was designed to handle 27 million passengers. But the existing
    two city airports handled 25 million passengers last year - and the city
    keeps attracting more visitors every year.
    "The airport is too
    expensive, too small and too much behind time," said aviation expert
    Dieter Faulenbach da Costa, who recently caused a stir when he proposed
    that the airport ought to be torn down.
    In an effort to salvage
    the mess, Hartmut Mehdorn, the hardnosed former boss of the German
    railway system with a reputation for turning around failing
    corporations, was named chief executive of the airport in early March.
    "The whole world says: it's not possible at all," Mehdorn said when he took over. "I say: It should be possible.
    "I just don't know how yet."


    _________________
    @avia.poncho
    Poncho (Admin)
    Poncho (Admin)
    Whisky Charlie


    Nouvel aéroport de Berlin Empty Re: Nouvel aéroport de Berlin

    Message par Poncho (Admin) Mer 8 Jan 2014 - 13:04

    Bon pas 2014 non plus alors je crois

    http://www.journal-aviation.com/actualites/25468-le-nouvel-aeroport-de-berlin-ber-n-ouvrira-pas-en-2014





    _________________
    @avia.poncho
    Poncho (Admin)
    Poncho (Admin)
    Whisky Charlie


    Nouvel aéroport de Berlin Empty Re: Nouvel aéroport de Berlin

    Message par Poncho (Admin) Lun 27 Juil 2015 - 16:37

    Une petite lecture en attendant l'ouverture (un jour) de cet aéroport ?
    http://www.bloomberg.com/news/features/2015-07-23/how-berlin-s-futuristic-airport-became-a-6-billion-embarrassment



    _________________
    @avia.poncho

    Contenu sponsorisé


    Nouvel aéroport de Berlin Empty Re: Nouvel aéroport de Berlin

    Message par Contenu sponsorisé


      La date/heure actuelle est Mar 5 Nov 2024 - 6:49